Skip to main content

2022 construction projects and expected delays

Here is the list of construction projects taking place on I-90 this summer and fall. Plan for delays through multiple areas and closures in August through November.

I-90 Homestead Valley Road to Coal Creek – Bridge Deck Repairs

Construction timeline

Summer 2022 – fall 2022

What can travelers expect?

Delays due to daytime and nighttime lane closures during the week as crews repair six bridge decks between North Bend and Snoqualmie Pass.

Bridge deck repairs this summer between North Bend and Snoqualmie Pass

I-90 Snoqualmie Pass East

Cabin Creek to Easton Phase 3 – Rebuild roadway, bridges & add lanes

Construction timeline

summer 2022 – fall 2028

What can travelers expect?

  • Delays due to intermittent single-lane weekday and weeknight closures followed by a traffic shift onto the new eastbound detour as crews widen I-90.
  • Follow us on Twitter @SnoqualmiePass for updates
Phase 3 of the I-90 Snoqualmie Pass East Project

I-90 S. Cle Elum Rd Bridges – Repair Bridge Decks

Construction timeline

summer 2022 – fall 2023

What can travelers expect?

Single-lane closures at night as crews work to install a detour bridge in preparation of a bridge deck repair project. Some delays expected and reduced speeds through the work zone.

Crews are installing a detour bridge this summer in order to repair the S. Cle Elum Bridges next summer

I-90 West Easton to Renslow Vicinity – Bridge Deck Repair

Construction timeline

summer 2022 – fall 2022

What can travelers expect?

Delays due to daytime and nighttime lane closures during the week as crews repair seven bridge decks from Easton to Kittitas.

Areas where crews will repair bridge decks in 2022

I-90 Oakes Ave Interchange to Yakima River Bridge – Replace Concrete Panels

Construction timeline

summer 2022 – fall 2022

What can travelers expect?

Delays due to single lane closures day and night through the week as crews repair sections concrete panels. Most of the work will take place at night, however, single lane closure will happen during the day to cure concrete panels.

Concrete panel replacement for 18 miles from Cle Elum to Ellensburg

SR 970 Chip Seal

Construction timeline

July through August 2022

What can travelers expect?

Delays due to weekday single-lane closures and piloted traffic as crews chip seal SR 970.

Minor delays through Roslyn as crews chip seal SR 970

Roadside Safety Enhancements – Guardrail Replacement

Construction timeline

late summer 2022 – late fall 2022

What can travelers expect?

Crews are working in multiple locations for 75 miles from North Bend to Ellensburg to replace guardrail and other safety features along I-90. Most of the work will be done at night with minor impacts to traffic.