Fauntleroy Terminal – Online Open House – Project timeline

WSF is early in the planning stage for replacement of the Fauntleroy ferry terminal. WSF is using a Planning and Environmental Linkages (PEL) study to consider potential solutions for how to replace the terminal. The PEL study, conducted in partnership with the Federal Highway Administration (FHWA), helps identify transportation issues, environmental concerns, community values and economic goals early in project planning.

After the PEL process, WSF will begin the National and State Environmental Policy Act (NEPA/SEPA) environmental review process, which will include more opportunities for community engagement and input.

Project timeline

  • Fall 2016
    Launched a public process to gather community input on how to improve the “Triangle route”
  • Fall 2017
    Near-term operational improvements at the dock
  • Spring 2019
    Launched new sailing schedule for Triangle route
  • 2019
    WSF releases 2040 Long Range Plan that recommends replacing Fauntleroy terminal
  • Spring 2021
    Fauntleroy Terminal – Trestle & Transfer Span Replacement project starts
  • Summer 2021
    Launched three advisory groups to advise WSF on options to replace the terminal
  • 2021 to mid-2023
    Planning and Environmental Linkages study
  • Late-2023
    NEPA/SEPA environmental review begins
  • 2023-TBD
    Environmental review, design and construction (schedule will depend on the results of the planning phase)