Project timeline

If WSDOT is awarded the RAISE grant funds, the projects are expected to follow the timeline shown below.

RAISE project timeline with milestones

Seattle

  • 2023
    Determine final scope of work and launch. Begin community engagement, conceptual design & evaluation.
  • 2024
    Develop conceptual design and cost estimate for community supported preferred option. Planning study complete.
  • 2025
    Finalize Preliminary Engineering (30% design level).

Spokane

  • 2025
    Determine final scope of work and launch.
  • 2026
    Community engagement to determine, evaluate, select and prepare cost estimates for 2-3 concepts.
  • 2027
    Develop conceptual design and cost estimate for community supported preferred option. Planning study complete.
  • 2028
    Finalize Preliminary Engineering (30% design level).
  • 2029
    Continue design development and community engagement.
  • 2030
    Continue design development and community engagement.
  • 2031
    90% design expected complete.

Toolkit

  • 2023
    Determine initial scope of work and launch. Advance GIS framework. Develop/test Transportation Equity Lab.
  • 2024
    Produce/test decision-making tools for critical activities. Hold Transportation Equity Lab, other workshops.
  • 2025
    Refine toolkit scope of work. Hold Transportation Equity Lab. Continue to test/refine/train on toolkit.
  • 2026
    Develop/test materials identified in updated scope of work. Hold Transportation Equity Lab.
  • 2027
    Revise materials/trainings. Complete/disseminate case study examples via trainings.
  • 2028
    Submit report on initial phases.
  • 2031
    Submit final report.