November 02 → November 05 2026

I-405/Northeast 132nd Street interchange closure in Kirkland

Date: Oct. 26-30
Time: Nightly from 9 p.m. to 5 a.m., beginning Monday night, Nov. 2 to Thursday night, Nov. 5.
Activity details: Crews will close the I-405/Northeast 132nd Street in Kirkland. Northeast 132nd Street under I-405 will also close.
Description: Crews working for the City of Kirkland will install speed cushions and adjust signage approaching the roundabouts to encourage traffic calming.
Traffic: Anticipate traffic delays on local streets in Kirkland approaching the closure. Detour routes cannot handle typical traffic volumes.
Contact the project hotline:425-354-3232

November 06 → November 09 2026

Northbound I-405 full closure in Bothell

Date: Nov. 6-9

Time: 11 p.m. Friday, Nov. 6 to 5 a.m. Monday, Nov. 9

Activity details: Crews will close northbound I-405 from SR 522 to SR 527 in Bothell. The Canyon Park Park & Ride will also close for the weekend.

Description: Crews will remove a section of the pedestrian bridge and the elevator tower at Canyon Park Park & Ride.

Traffic: Anticipate traffic delays in Bothell approaching the closure.

Contact the project hotline: 425-354-3232

November 06 → November 07 2026

I-405/Northeast 85th Street interchange closure in Kirkland

Date: Nov. 6-7
Time: 9 p.m. Friday to 5 a.m. Saturday
Activity details: Crews will close the northbound/southbound I-405 ramps (Exit 18) and Northeast 85th Street from Sixth Street South to 120th Avenue Northeast.
Impact type: Overnight
Description: Crews will work on electrical installation.
Traffic: Anticipate traffic delays on local streets in Kirkland approaching the closure. Detour routes cannot handle typical traffic volumes.
Contact the project hotline: 425-224-2423

November 13 → November 14 2026

Eastbound and westbound SR 522 closure in Bothell

Date: Nov. 13-14
Time: TBD, Friday, Nov. 13 to TBD, Saturday, Nov. 14
Traffic: Anticipate traffic delays in Bothell approaching the closure. Detour routes cannot handle typical traffic volumes.

Contact the project hotline: 425-354-3232

November 20 → November 21 2026

Eastbound and westbound SR 522 closure in Bothell

Date: Nov. 20-21
Time: TBD p.m. Friday, Nov. 13 to TBD a.m. Saturday, Nov. 14
Traffic: Anticipate traffic delays in Bothell approaching the closure. Detour routes cannot handle typical traffic volumes.

Contact the project hotline: 425-354-3232