Timeline
- Advertisement Date
March 14, 2022 - Bid Opening
April 13, 2022 - Award
May 28, 2022 - Begin Construction
July 2022
Funding
Paving
Design $361,400 and construction $4,586,800
Roundabout
Pre-design effort (current stage) $50,800
Design $118,220 and construction $658,495