Timeline

  • Advertisement Date
    March 14, 2022
  • Bid Opening
    April 13, 2022
  • Award
    May 28, 2022
  • Begin Construction
    July 2022

Funding

Paving
Design $361,400 and construction $4,586,800

Roundabout
Pre-design effort (current stage) $50,800
Design $118,220 and construction $658,495