SR 510/Yelm Loop – New alignment phase 2 online open house – Updated timeline

This image shows a timeline of the project, including the following: 
•	Public involvement/stakeholder engagement, started May 2018 and ends in August 2021
•	Preliminary design, started April 2018 and ended January 2019
•	NEPA supplemental environmental assessment, started September 2018 and ends in September 2020
•	Permitting, starts in October 2020 and ends in January 2021
•	Right of way, started in August 2017 and ends in June of 2021
•	Final design, started February 2019 and ends February 2021
•	Bidding/award, starts in March of 2021 and ends in June of 2021
•	Construction, starts in July of 2021 and ends in December of 2023