Skip to main content
WSDOT online open houses

What to expect in 2025: key milestones

Construction is scheduled 2025 to 2027

The project’s first season in 2025 will span from May through October. During this time, crews will construct the Lake Creek and Unnamed tributaries to Friday Creek culverts. The second and third season of work will be in 2026 and 2027, respectively and will consist of constructing the Chuckanut Creek and Unnamed tributary to Lake Creek sites, in addition to completing stream restoration and landscaping work at the Unnamed tributaries to Friday Creek site.

2025 Project timeline

Lake Creek – Milepost 246

Unnamed Tributary to Friday Creek – Milepost 241

Lake Creek

Construction will begin in May 2025 at the Lake Creek site (milepost 245). A median bypass road will be constructed between northbound and southbound I-5 lanes to move traffic away from the work area.

Once traffic has been moved onto the median bypass road then excavation and removal of the old fish barrier will occur, followed by installation of the new culvert. Once the new culvert has been backfilled and the roadway restored, traffic will move back onto the existing roadway. When one side of I-5 has been constructed, the median bypass will be reconfigured to support work on the other side of I-5.

Most of the work at the Lake Creek site will be completed by August 2025.

Friday Creek

Beginning in August 2025, and after the Lake Creek culverts have been installed, work will commence at the Unnamed Tributaries to Friday Creek site (milepost 241). The order of work will occur very similarly to what was done at Lake Creek. People who travel on Lake Samish Road will experience a guided detour route in September 2025 while the road is closed just west of I-5. In 2026, crews will continue in stream and restoration work.

During the first season of construction, crews should be off the roadway by November 2025.

Map showing locations of project work zones

Traffic bypass on the I-5 median

Travelers on I-5 will use the two-lane temporary bypasses through the summer while the Lake Creek culverts are under construction.

How long will traffic be on the bypass?

Bypass roads on I-5 will be constructed to divert traffic around the work area. For 2025, this will occur at the Lake Creek and Unnamed tributaries to Friday Creek sites (mileposts 245 and 241). Construction of these temporary roads will begin in May, and completion will occur in October this year. In 2026, similar bypass roads will be constructed at the Unnamed tributary to Lake Creek (milepost 246) and Chuckanut Creek sites (milepost 247).

Graphic showing median bypass route
Graphic showing bypass lane configuration