Geiger Field Interchange Reconstruction – Medical Lake/SR 902 Interchange Reconstruction progress

Roundabout progress

Work is completed on the two northern multilane roundabouts. Crews constructed the roundabout at the connection to SR 902 and Geiger Blvd. last summer. The second roundabout at SR 902 and the westbound on and off-ramps to Interstate 90 was completed in early fall. During which time, crews implemented a 10-day shutdown of the ramps and intersection to construct the entirety of the roundabout.

The third and final roundabout near the south business park at the intersection with the eastbound I-90 on and off-ramp terminals, along with the connection to the Spokane Transit Authority will be completed this summer.

Medical Lake interchange aerial view

New bridge overcrossing

Work on the new overcrossing has been suspended due to COVID-19.

The new bridge along with the rest of the Medical Lake/SR 902 interchange reconstruction will be completed late summer to early fall of 2020.